Glamorgan Spring Bay General Manager David Metcalf, Hoabrt Water
CEO Dr Christine Mucha and Mayor Bertrand Cadart drinks a toast to
the successful implementation of the Swansea Water Deed (story below).

Swansea Water Solution Closer
A reliable, treated water supply for Swansea appears much closer after a Glamorgan Spring Bay Council workshop with the faciltators, Hobart Water, and invited members of the community.
The meeting was arranged by Council following the refusal by a majority of councillors to endorse the Swansea Water Deed, an agreement between Council, State Government Treasury and Hobart Water for the construction of a 400 megalitre dam beside the Meredith River and the provision of a water treatment plant.
Treasury estimates revealed a financial blowout of approx. $3,000,000 in a total cost of $8,467,004. A previous estimate by Burnie consulting engineer, Bill Enkelaar, placed the figure at $5,500,000.
The Government proposes contributing a total of $1,920,000 to Hobart Water over 4 years to subsidise various financial offsets.
An officer from Treasury said the contribution was a set amount, could not be increased, wasn't required to be repaid and must go to Hobart Water.
Should Council again refuse to sign the Deed and attempt construction themselves, the subsidy would not be paid to Council.
Terms of the Deed show that Hobart Water are required to call tenders for construction and supply.
Cr Howard Harris repeated a statement he made at a meeting of Council on 3rd June when he said: "Council is unable to endorse the Swansea Water Deed as presented because we can't commit to the estimated cost of $8.5 million."
Hobart Water Corporation Chief Executive Officer, Dr Christine Mucha, who was accompanied at the meeting by the corporation's Finance Manager and Chief Engineer, said: "The quote should be considered an estimate only. There has never been any intent to maximise upon the $8.5 million. If it can be done cheaper, then it will be .... in which case Council commitments  would not be so great.
"We are very aware of costs (as is the Board of Hobart Water). Only this morning we were checking prices for pipeline and other items."
The Treasury model budget shows contingencies in the contract have been nominated at 30% and escalating costs allowance over one year at 10%.
A timeline for the project shows work starting immediately with the dam constructed by January 2009 and water treatment plant commissioned by October 2009.
Councillors are presently attending workshops on the Council's budget and matters arising from the meeting will be considered at the next meeting of Council.